prod:oracle_primavera_duration_percent_complete
Unterschiede
Hier werden die Unterschiede zwischen zwei Versionen angezeigt.
Beide Seiten der vorigen RevisionVorhergehende Überarbeitung | Nächste ÜberarbeitungBeide Seiten der Revision | ||
prod:oracle_primavera_duration_percent_complete [2015/10/18 17:29] – gpipperr | prod:oracle_primavera_duration_percent_complete [2015/10/18 17:33] – [Der Typ % Complete Type = Duration % complete] gpipperr | ||
---|---|---|---|
Zeile 178: | Zeile 178: | ||
{{ : | {{ : | ||
+ | ====Der Typ "% Complete Type => Units % complete" | ||
+ | "Used when resources are assigned to an activity and “actual units worked” will be tracked" | ||
+ | * The only drawback of this method is that hours expended do not necessarily equal the progress achieved | ||
+ | Formel:< | ||
+ | ====Der Typ "% Complete Type = Physical % complete" | ||
+ | "Use if you record progress based on personal judgment" | ||
+ | * Physical % Complete value will be entered by the user manually | ||
+ | * Caution: The user must adjust the Remaining Duration as this is not calculated by P6! | ||
+ | |||
+ | |||
+ | Der Typ ist am einfachsten einsetzbar, hier wird einfach der Prozentsatz UND der Remainig Effort gesetzt. | ||